> Aircraft Hangar Erection Procedure
The images below will take you through the main steps of assembling a 25m (82ft) Span x 36m (128ft) Long EFASS with a
Heli-Door each Gable End.
Setting out foundation layout.
Fixing footplates into position.
Preparing spans to form first module.
Preparing lift of first module.
Preparing lift of second module.
Installing covers.
Lifting end spans.
Fixing end spans into position.
Raising door frame.
Assembling heli-door.
Fixing fabric panels in door.
Completed hangar.