> Helicopter and Aircraft Hangar Erection Procedure
The images below will take you through the main steps of assembling a 20.4m (66.9ft) Span x 28m (91.8ft) Long EFASS with a Fast Jet Door each Gable End.
Container ready to be unloaded.
Spans bolted up to form first module.
Module hand winched into vertical position.
Second module being lifted.
Perlins fixed between first and second modules.
Kieder edged PVC is then fed up the aluminium profile and hand winched over the module.
Remaining covers installed to form solid mid section.
Both adjacent end spans are winched up and secured using the same method.
Covers installed into end modules.
Doors being assembled.
Checking Door Operations.
Building complete.