> Helicopter and Aircraft Hangar Erection Procedure



The images below will take you through the main steps of assembling a 20.4m (66.9ft) Span x 28m (91.8ft) Long EFASS with a Fast Jet Door each Gable End.



Military helicopter and aircraft hangar with Fast Jet Door Erection stage Military helicopter and aircraft hangar with Fast Jet Door Erection stage Military helicopter and aircraft hangar with Fast Jet Door Erection stage Military helicopter and aircraft hangar with Fast Jet Door Erection stage

Container ready to be unloaded.

Spans bolted up to form first module.

Module hand winched into vertical position.

  Second module being lifted.





Military helicopter and aircraft hangar with Fast Jet Door Erection stage Military helicopter and aircraft hangar with Fast Jet Door Erection stage Military helicopter and aircraft hangar with Fast Jet Door Erection stage Military helicopter and aircraft hangar with Fast Jet Door Erection stage

Perlins fixed between first and second modules.

Kieder edged PVC is then fed up the aluminium profile and hand winched over the module.

Remaining covers installed to form solid mid section.

Both adjacent end spans are winched up and secured using the same method.






Military helicopter and aircraft hangar with Fast Jet Door Erection stage Military helicopter and aircraft hangar with Fast Jet Door Erection stage Military helicopter and aircraft hangar with Fast Jet Door Erection stage Military helicopter and aircraft hangar with Fast Jet Door Erection stage

Covers installed into end modules.

Doors being assembled.

Checking Door Operations.

Building complete.